Deputy CEO PFC CSKA responsible for the stadium construction matters Vladimir Sudarikov told to pfc-cska.com about the latest news from the 3rd Peschanaya ul.
— We have finished solid constructions in the South and West tribunes. The roof construction above South tribune is almost finished: only one section is still open, as the crane needs some space for operating. The construction of the roof above the West tribune has started recently. The inside works are already under way, inside walls for under tribune facilities are being installed. In particular, walls for the future dressing rooms are already made.
Till the end of the year we are planning to finish South-West administrative building: now we are finishing the last 11th floor. Last week the façade works were started. In the East, the works on the upper part of the stands are under way.
The hotel building at the North-East reached the 2nd floor. North tribune is lower so far, underground works are held there. By the end of the year the underground part of the stand will be finished, we shall reach the ground level.
At the separate parking the façade works are being done. Inside the technical pipelines and networks are being fixed – ventilation, pipelines, fire alarm, lighting.